Summer Schedule and Notes
Current List of Things to Do:
- Leaning Tower of Pisa (weight distribution) and Solidworks Model
- Update Twiki Page
- Wrap up old data
- Conclusions/ Observations
- Post some trial data
- What parameters didn't work well
- What parameters seem to work well
- Work to be done
Week 1 - June 21-June 25
- Test track data w/ accelerometer
- Brainstorm foot ideas
- Revise test track experiment sheet
- Familiarize with all test track parameters
- Propose questions on what a "good foot" is
Week 2 - June 28-July 2
- Refine test to get key foot characteristics (w/minimal tests)
- Analysis tools to ID what a "good foot" is
- 2nd Generation Foot Design
Week 3 - July 5-July 9
- Familiarization with new leg
- Test dactyl foot with new leg
- Analyze dactyl foot for CMU
- Tools to ID what a "good trajectory" is
- Work on mountable feet
- Dana and Miguel (for the test track)
- Ji and Alan (for toybot)
- Help Miguel with running foot
Week 4 - July 12-July 16
- Do Lamellae Friction tests without claws (on new leg)
- Eliminate the degree of freedom that allows the foot to rotate clockwise/counterclockwise about the ankle
- The claws and the rotation about the ankle yield inconsistencies in the data
- Make sure the distance of the claw to the crank is equal to that on the CMU leg
- Optimize trajectory parameters
- Fz is not constant because phi is constant
- Make Fz constant by varying phi
- Fx and Fy are approximately the same
- Fy should be greater than Fx (something like 3:2 ratio)
- Do Dactyl claw tests (on new leg)
- Unbent
- Bent
- Send results to CMU
- Work on mountable feet
- Dana and Miguel (for the test track)
- Ji and Alan (for toybot)
Week 5 - July 19-July 23
- Make new feet for CMU
- Test new feet for CMU
Week 6 - July 26-July 30
Week 7 - Aug 2-Aug 6
- Receive robot body
- 3rd round of trajectory tests
Week 8 - Aug 9-Aug 13
- 1st round of COMPLETE robot climbing tests
Week 9 - Aug 16-Aug 20
Week 10 - Aug 23-Aug 27
Ongoing List:
- SDM
- Familiarize w/ Matlab
- Familiarize w/ CAD (Solidworks)